subscribesubscriber servicescontact usabout ussite map
 
December 13, 2005

Long warranty for tanks

Concerns over defects push GT to take 15 years

      TRAVERSE CITY - Concerns over "latent defects in construction" at Grand Traverse County's septage treatment facility pushed the county to take the longest warranty it could obtain on reconstructed tanks - 15 years.
      Early last week the five local townships that fund the facility wanted a warranty guaranteed by a bond and were willing to settle for a five-year term. The 15-year warranty is not backed by a bond.
      Gourdie-Fraser/Christman LLC, the designer/builder of the failed facility, offered the townships their choice.
      "After that meeting some people told me I'm selling the farm to take the five-year instead of the 15-year warranty," said Peninsula Township supervisor Rob Manigold.
      After the county's engineering expert, NTH Consultants, recommended the longer warranty Manigold said he'd be "more comfortable" with 15 years.
      Garfield, East Bay, and Elmwood townships also supported the 15-year warranty. Acme Township supervisor Bill Kurtz voted no. He preferred to have at least some, if not all of the warranty guaranteed by a bond.
      NTH said that given the long-term financial stability of the Christman Company the longer warranty would better serve the interests of the county, "given the latent defects in construction" of the facility.
      Defects that have not been discovered by NTH and might manifest themselves years down the road makes the long-term warranty superior, NTH told county officials.
      Most defects should be evident within two years, but defects in materials could take as long as seven years to show up, NTH said.
      Approval of the contract amendment will allow Gourdie-Fraser/Christman to begin taking apart the membrane tank building that collapsed in June and released 150,000 gallons of partially treated sewage. The deconstruction will allow NTH to look for more possible flaws in how the tanks were built.
      Depending on what NTH finds it may recommend the other two concrete tank buildings also be demolished. Like the tank that collapsed, the other tanks are missing reinforcing steel and weren't designed to the industry standard to prevent leaks and cracking.
      A decision on repairs or replacement will be made in January.

See Related Stories:
      Septage plant repairs at issue - December 2, 2005
      Plant designer says it didn't know about standard - November 10, 2005
      Septage repairs outlined - November 10, 2005
      Consultants to offer final septage report - November 9, 2005
      Subcontractor questions collapse fault - November 4, 2005
      Septage report cites company's omission - October 19, 2005
      Acme wants Houlihan removed from investigation - October 15, 2005
      Septage plant collapse explanation coming - October 15, 2005
      County officials back Houlihan in septage investigation - October 7, 2005
      Septage 'debacle' questioned; Supervisor wants all info - October 4, 2005
      Public awaits report on collapse of septage plant - September 27, 2005
      Taxpayers won't foot bill for septage plant repairs - July 26, 2005
      Officials looked for 'spin' in septage plant collapse - July 23, 2005
      Septage spill situation becoming muddled, attorney says - July 23, 2005
      Septage plant repairs tagged at $2 million - July 19, 2005
      Health risk from septage plant failure said minimal - July 19, 2005
      Well owners near septage plant fear contamination - June 25, 2005
      GT County's septage treatment plant may reopen - June 22, 2005
      Septage plant 'structural failure' is investigated - June 21, 2005
      Burst tank rocks GT County's new septage plant - June 19, 2005

See Related Editorials:
      Plant collapse exposed failed system - November 15, 2005
      Aloia deserves credit for putting public first - October 2, 2005
      Septage plant solution must be public process - September 18, 2005
      Finally, facts to ordain who pays for new septage plant - September 13, 2005
      Septage plant contract puts the taxpayers last - September 6, 2005
      Plant collapse inquiry is stuck in 'spin' cycle - August 3, 2005

Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Find a new or used car
Find a new home
Find a new job

Top Autos & More

Top Stuff

Top Real Estate

Top Rentals